Built once, built right — a fully coordinated General Construction proposal prepared for Mr. Inigo & Mrs. Tessa Arellano, La Granja Estates, Bukidnon.
Having reviewed the Tender Documents, plans, specifications, and completed our site inspection on 16 July 2026, JMG Construction & General Merchandise — operating under the JMG Design & Build brand — hereby confirms our intent to undertake the complete construction of the 517 Courtyard House. We understand this project's requirements and are prepared to execute the Works in accordance with the approved Architectural, Structural, Electrical, Mechanical, Plumbing, Electronics, and other relevant Design Documents, except for items expressly identified as Owner-Supplied Materials.
Before pricing a single line item, we submitted nine formal clarification requests to ARCLAB covering payment terms, liquidated damages, VAT treatment, fire-protection and electronics scope, OSM schedule interfaces, and the La Granja Estates construction guidelines — we caught these questions before pricing, not after breaking ground. Every answer received in Bid Bulletin No. 1 is reflected throughout this proposal, cited by clause, so ARCLAB can see exactly what we clarified and confirmed before this number was set.
We intend to mobilize in September 2026. Our proposed Contract Time is 18 months (540 calendar days), with the full phase breakdown and justification set out in the Construction Schedule tab. We are committed to delivering quality workmanship, disciplined project management, and a smoother, more professional client experience — with close attention to design intent, testing, commissioning, and final turnover.
This bid covers the complete Tender scope of works as a single General Construction Contract, per Cl. 2.7 and Bid Bulletin No. 1 — the Owner intends to award one contract covering the entire scope defined in the Tender Documents. Tap any division to open its itemized detail.
Following the scope revision dated 24 August 2026 (removal of maid's room, TV room, and associated outdoor spaces), the updated total Gross Floor Area is 471.95 sq.m. (revised from 506.95 sq.m.). The Ground Floor / Second Floor split shown below reflects this change and remains an indicative massing estimate consistent with the approved Architectural Plans — exact per-room areas will be confirmed against ARCLAB's revised Room Schedule / Area Take-off. The room inventory is reconciled against ARCLAB's Interior Design Perspectives (Tender Document C) and cross-checked against named spaces priced in the Detailed BOQ (concrete countertops, tile schedules, fixture schedules — "In BOQ" tag).
Five confirmed perspectives from ARCLAB's Interior Design and Architectural Design sets — approach, foyer, living, dining, and kitchen — pulled directly from the issued Tender Document C, not estimated or placeholder art. Swipe or use the arrows to page through.
Dearest Inigo and Tessa,
Warmest greetings to both of you! I wanted to write to you personally, not just as a bidder, but as the person whose team will be right there with you on your lot in La Granja Estates over the next year and a half.
When Team JMG visited and walked the site last July 16, we did more than measure dimensions against the blueprints. We stood on the very ground where your family will build memories, welcome loved ones, and live day to day. For us, seeing the actual location changes everything — it's the difference between merely calculating a floor area and taking care of someone's future home.
That is also why, before putting together our figures, we reached out to ARCLAB with nine detailed clarification questions covering payment terms, delivery schedules for roofing and glazing, and fire protection and electrical coordination. We did this not out of formality, but because we want to give you honest, reliable numbers from the start. You deserve a partner who anticipates the important details early on, so everything runs smoothly once work begins on site.
To be completely transparent, just as I would hope for if this were for my own family, our bid may not be the lowest figure on your table. We carefully priced this proposal to account for real lead times, a realistic 18-month construction timeline, and thorough inspections at every phase. If the lowest cost is the primary consideration, we completely understand. But if your priority is turning your key after eighteen months with complete peace of mind, knowing every peso was spent wisely and well, then we would be truly honored to build this home for you.
In the following pages, you will see our full work plan, timeline, clear payment milestones tied to quality inspections and safety standards, and the key personnel dedicated to your site. More than any document, please know that you are not just a client or line item to us — you are the heart of this entire project.
Thank you for the opportunity to visit your property and share in your vision. Whatever your decision, we are sincerely grateful. Should you wish to discuss anything further or ask any questions, please feel free to reach out anytime. I am always at your service.
With warm regards and respect,
All materials specified below are sourced from trusted suppliers and carry performance warranties. Each category is organized by building system; expand any to review the specific products and standards for that component.
Two Fully Priced Structural Options: Version 1.0 OB (Steel Deck, default, ₱20,130,322.29) and Version 1.0 OA (Standard Framing, ₱20,783,226.04). Switch between them using the toggle below to see every cost figure recalculate — same scope, same quality, different methods. All figures are VAT-inclusive (12%) by default per Cl. 7.36 and Bid Bulletin No. 1; use the hero toggle to compare VAT-exclusive figures. Division subtotals are the single source of truth driving every number on this page; the audit banner below confirms they reconcile.
We priced this two ways rather than pick one for you. Standard Framing is the conventional approach — full wood formwork and full slab reinforcement. Steel Deck replaces the wood formwork under the suspended slabs with permanent 0.76mm G550 steel decking, which also reduces the rebar needed — faster to build, with the same structural integrity, at a lower price. Switch the toggle in the hero (or the buttons below) to see every figure on this page recalculate for either option.
| Total Construction Cost (w/o Contingency) | |
| Contingency / Overhead / Profit | |
| Total Construction Cost (w/ Contingency) | |
| VAT (12%) | |
| GRAND TOTAL |
Full line-item detail shown per division for the selected structural option — every quantity, unit rate, and amount below is drawn directly from the Quantity Estimates workbook and verified to reconcile exactly to its division subtotal. Nothing is summarized or hidden.
Per Cl. 1.2 and Bid Bulletin No. 1, the Owner's target is Substantial Completion in fifteen (15) calendar months from Notice to Proceed. Based on our proposed construction methodology, resource allocation, and disciplined phase sequencing — including the schedule interface with OSM roofing (90–120 day lead time) and glazing (60-day lead time) deliveries — JMG proposes an alternative Contract Time of eighteen (18) calendar months (540 days), per our Construction Schedule on file (Doc. No. JMG-CS-517CH-001). We caught this interface risk before pricing it: compressing the schedule to 15 months would place OSM-dependent finishing work at direct risk of delay outside JMG's control.
| Phase | Description | Duration | Window |
|---|
Per Cl. 10.2/10.3 and Bid Bulletin No. 1: no Mobilization Advance Payment applies to this Contract — JMG self-funds all mobilization activities and recovers such cost through approved Progress Billings, with no Advance Payment Bond required. Progress Billings are proposed against nine measurable, verifiable milestones, each mapped directly to the Construction Schedule phases above.
Condensed from JMG's project-specific QA/QC Plan (JMG-QAQC-517CH-001) and Construction Safety & Health Plan (JMG-SH-517CH-001), both prepared for tender submission per Bid Bulletin No. 1.
Baseline Schedule, Construction Methodology, Safety Program, and QA/QC Plan submitted for sanction before mobilization. No construction activity begins without written administrative authorization.
Controlled drawing/spec register, shop drawing and material submittal workflow, formal RFI/RFA process, and revision control — no material is ordered until technical review is complete.
Hold / Witness / Review / Surveillance points on every critical activity. Concealed work — reinforcement, embedded MEP, waterproofing — is never covered until the required inspection is obtained.
Concrete slump/compression testing, reinforcing steel tensile/bend testing, plumbing pressure/leak testing, electrical insulation-resistance and grounding tests, and full mechanical commissioning — each with certified reports.
Identify → contain → evaluate → correct → re-inspect → close. Every NCR is tracked to closure with supporting records — nothing gets quietly re-worked off the books.
Qualified Safety Officer, daily toolbox meetings, mandatory task-specific PPE, stop-work authority for any worker, and a full emergency response network established before mobilization — aligned to RA 11058 and DOLE D.O. 198-18.
JMG confirms compliance with the La Granja Estates Declaration of Covenants, Conditions & Restrictions (Cl. 3.12): 8-foot olive-green G.I. sheet or tarpaulin site fencing for the duration of construction, ₱100,000 refundable Construction Bond, ₱40,000 Technical Evaluation Fee, construction-worker ID and hard-hat requirements, controlled delivery and stockpiling on the Owner's own lot only, noise control before 7:00 AM / after 6:00 PM, and site clean-up within 30 days of completion. These items are priced explicitly in our Preliminaries division (Division I) rather than assumed.
JMG Construction & General Merchandise operates as a Registered Contractor with a full in-house complement of licensed engineers and architects — not a labor-only outfit subcontracting its technical judgment.
JMG is a Certificate-of-Registration-holding entity (certificate on file with this bid submission). Project-specific site assignments — Project Manager, QA/QC Engineer, and Safety Officer — will be confirmed upon award and mobilization, consistent with our QA/QC Plan and Safety & Health Plan.
Provided in good faith for verification of JMG's residential construction, architectural, and fit-out experience — every reference below can be contacted directly.
| Client | Project | Location | Contact |
|---|---|---|---|
| Mr. Angelito B. Escoto | Construction of 2-Storey Casa Lian Residence | Kisanlu Subdivision, Iponan, Cagayan de Oro | +63 947 337 0093 |
| Mr. Oscar & Mrs. Cherill Mabao | Construction of 2-Storey REMA Residence | Kisanlu Subdivision, Iponan, Cagayan de Oro | oscarmabao@gmail.com |
| Mr. Carlito Mariaca Jr. | Residential Completion — Mariaca Residence (Interior & Exterior Architectural / Fit-Out) | Opol, Misamis Oriental | +63 994 021 3099 |
| Mr. Christopher & Mrs. Joni Muñez | Bali-Japanese Vision — Hoshiyama Residence | Dampalan, Sergio Osmeña, Zamboanga del Norte | +63 928 251 3746 |
On 24 July 2026, JMG submitted nine formal clarification requests to ARCLAB under Section 2.4 of the Instructions to Bidders. Bid Bulletin No. 1 (issued 3 August 2026) answered each. This is presented here as a credibility asset, not fine print — it is exactly what we confirmed before this number was set.
| Date | Change |
|---|---|
| 2026-08-18 | Initial interactive bid proposal published, incorporating Bid Bulletin No. 1 responses and JMG's Construction Schedule (18-month proposed Contract Time). |
| 2026-08-19 | Final estimates updated from the 517 Courtyard House Quantity Estimates workbook: full line-item BOQ (500+ items per option, replacing representative excerpts), and two fully-priced structural framing options — Standard Framing (₱21,766,301.12) and Steel Deck (₱21,113,397.36, shown by default). Grand Total, all division subtotals, Cost Summary, and Payment Schedule milestones now recalculate live from the selected option. |
| 2026-08-27 | ARCLAB Scope Revision (per email 2026-08-24): Maid's room, TV room, and associated outdoor spaces (lanai, backyard porch) removed from scope — approximately 35 sq.m. of enclosed space and 20 sq.m. of outdoor slab areas. Exterior columns, footing, and tie beams for these removed areas are retained per ARCLAB directive, so the reduction is smaller than a straight floor-area cut would suggest — the retained structural elements remain JMG's responsibility, and labor and material rates were comprehensively re-estimated line-by-line across every affected division rather than pro-rated. This represents honest, line-by-line recalculation rather than assumption or approximation — evidence of thorough analysis before pricing. Updated Grand Total (VAT-inclusive, Steel Deck option): ₱20,130,322.29 (down ₱983,075.07 from ₱21,113,397.36). Standard Framing option updated in parallel: ₱20,783,226.04 (down ₱983,075.08 from ₱21,766,301.12). Gross Floor Area revised: 506.95 sq.m. → 471.95 sq.m. Payment Schedule restructured with realistic phase-based milestones (10 instead of 9) tied to cost concentration in each construction phase. |