517 Courtyard House: Earthworks Under Way in Baungon, Bukidnon

Project Update: Earthworks & Foundation (Week of November 8, 2026)

Site work is moving on 517 Courtyard House, a 2-storey residential project in Baungon, Bukidnon. House construction here is now in the Earthworks & Foundation stage.

What’s happening on site

  • Excavation: ongoing inside the perimeter fence.
  • Plotting (layout): ongoing, so every line is set before we build.
  • Procurement: we have started the initial order of rebars, formworks, scaffolding and other materials. Delivery is expected next week.

Two items we’re managing

The excavator’s pin was damaged by large rocks in the excavation area. The unit is under repair, so excavation is slower until it’s done.

We are also waiting on the finalized schedule and structural drawing. Cutting and forming for the footings will not start until we have them. Footings carry the whole house, so we build from final drawings, not assumptions.

Next steps

  1. Continue excavation and plotting, and complete the excavator repair.
  2. Receive the rebars, formworks, scaffolding and other materials next week.
  3. Begin cutting and forming for the footings once the finalized schedule and structural drawing are released.

Every JMG project comes with a weekly progress report. Delays are named, causes are explained, and next steps are clear.

Planning a home in Northern Mindanao? Message us to start your design-build conversation.

Frequently Asked Questions

What stage is the 517 Courtyard House project in?
The project is in the Earthworks & Foundation stage. Excavation and plotting (layout) are ongoing at the Baungon, Bukidnon site.

What slowed progress this week?
Two items. The excavator’s pin was damaged by large rocks in the excavation area and is being repaired. We are also waiting on the finalized schedule and structural drawing needed to begin the footings.

Why can’t footing work start yet?
Cutting and forming for the footings begins only after we receive the finalized schedule and structural drawing. Footings carry the whole house, so JMG builds from final drawings, not assumptions.

When are the construction materials arriving?
Initial procurement of rebars, formworks, scaffolding and other materials has started. Delivery is expected next week.

Does JMG Design & Build give clients regular progress updates?
Yes. Every JMG project comes with a weekly progress report covering milestones, delays and their causes, site photos, and next steps.

JMG Construction & General Merchandise, operating as JMG Design & Build. Design. Build. Value.

Leave a Comment

WhatsApp

Premier Architectural Design and Building Construction Services in Cagayan de Oro Northern Mindanao, Philippines

Viber

Connect instantly with JMG Construction & General Merchandise through Viber. Scan the QR code to chat and learn more about our services. Reach out today via Viber!

QR code for JMG Construction & General Merchandise business account on Rakuten Viber with a prompt to scan and chat.
Scan the QR code to instantly connect with JMG Construction & General Merchandise on Rakuten Viber.
Contact us on WhatsApp or Viber!

How We Prepare Proposals!

With our extensive experience, commitment to quality, and dedication to sustainability, we are ready to make your dream project a reality.

Scroll to Top